Project 27
“San Diego Pipeline No. 5 & Lake Skinner Outlet Conduit Repairs”
MWD Specification No. 1526

  
Project Description

Location: Winchester , CA
Owner: Metropolitan Water District of Southern California
Contract Start Date: December 2005
Contract Completion Date: April 2006
Contract Amount: $1.378,000.00

The project consists of furnishing and installing carbon-fiber reinforcing lining to the interior surfaces of a portion of the 96-inch diameter San Diego Pipeline No. 5 and the 162-inch diameter Lake Skinner Outlet Conduit. Additional work includes the removal of a section of the 162-inch diameter pre-stressed concrete cylinder pipe, installation of a 15 inch diameter steel liner within the concrete cylinder pipe and installation of a 163-inch diameter welded steel pipeline section. All repair work is to be performed during the two separate shutdown periods working 24/7.